YTPS Units to Be Fully Operational by January 15: Deputy CM

IO_AdminAfrica8 hours ago4 Views

Quick Summary

  • Yadadri Thermal Power Station (YTPS): Deputy CM M. Bhatti Vikramarka announced that the 5×800 MW supercritical technology plant will be completed by January 15 next year.
  • Delay & Environmental Clearances: the Congress government obtained fresh environmental approvals after re-conducting a public hearing in February 2024,following delays under the previous BRS administration due to national Green Tribunal (NGT) rulings in October 2022.
  • Employment Initiatives:

– Appointment letters handed over to 500 families who gave up land for YTPS as part of rehabilitation efforts.
– Compassionate job offers extended to kin of Telangana Power generation Corp. employees who died in service-totaling appointments for a second time under the current government.

  • CSR Efforts Around Plant Operations:

– Free world-class education and healthcare promised for villages near YTPS using CSR funds.
– Infrastructure enhancements approved, including ambulances, cement-concrete roads, flyovers, and funding for road works land acquisition.

  • Power Sector Updates: State spending includes ₹17,000 crore on free power:

– Coverage includes power to agricultural pump sets (29 lakh) and monthly free energy allocation (200 units each) for approximately 51 lakh families.


Indian Opinion Analysis

The commissioning of Yadadri Thermal Power Station marks both infrastructural progress and an attempt by Telangana’s Congress-led administration to address previous project delays attributed to environmental non-compliance under the BRS regime. While timely completion could alleviate economic burdens caused by such setbacks, genuine focus on ensuring lasting practices remains crucial given past NGT interventions.

the government’s dual strategy-bolstering employment through rehabilitation initiatives while allocating funds toward infrastructure advancement around YTPS-aims at garnering local support amid broader concerns about equitable resource distribution like free electricity schemes. However, delivering on promises of free education and healthcare near plant sites demands vigilance against potential implementation gaps or fund mismanagement.

Large-scale investments into renewable capacity remain vital alongside thermal power advancements given India’s longer-term climate commitments. Efficient monitoring systems that align operational goals with compliance frameworks may ensure smoother future projects while fostering greater public trust.Read more

0 Votes: 0 Upvotes, 0 Downvotes (0 Points)

Leave a reply

Recent Comments

No comments to show.

Stay Informed With the Latest & Most Important News

I consent to receive newsletter via email. For further information, please review our Privacy Policy

Advertisement

Loading Next Post...
Follow
Sign In/Sign Up Sidebar Search Trending 0 Cart
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...

Cart
Cart updating

ShopYour cart is currently is empty. You could visit our shop and start shopping.