# Bengaluru suburban rail only 20% done, to use European signalling

2026-08-12T22:33:31+00:00 | Governance | Indian Opinion Desk

Corroboration: 1 independent outlet

The Bengaluru Suburban Transport Project has achieved only 19.9% physical progress in three-and-a-half years as of July, says implementing agency K-RIDE. Tenders have been invited for viaduct works on corridor-2 and packages covering 22 km on corridor-4, while land acquisition for the Akkupete depot is under way. K-RIDE has confirmed it will use the European Train Control System Level-2 across all corridors, replacing the earlier planned communications-based train control. The same system will be used for India's Mumbai-Ahmedabad high-speed rail. A double-decker structure is planned along Mohan Kumar Road, with a road flyover below the suburban rail line.

## Coverage

- timesofindia.indiatimes.com <https://timesofindia.indiatimes.com/city/bengaluru/suburban-rail-project-only-20-physical-work-done-trains-to-use-european-signalling-system/articleshow/133191744.cms>

Tags: Bengaluru suburban rail, ETCS, infrastructure, K-RIDE, progress, signalling
Canonical: https://indianopinion.org/bengaluru-suburban-rail-only-20-done-to-use-european-signalling/
License: Summary and commentary (c) Indian Opinion, reusable with attribution. Facts belong to the linked sources.
Cite: https://indianopinion.org/bengaluru-suburban-rail-only-20-done-to-use-european-signalling/#story-in-brief

Review state: restored archive article, accurate at time of publication, not offered to search indexes.