Quick Summary
- Bangalore International Airport limited (BIAL) issued a Request for Proposal (RFP) to appoint contractors for enabling works in the second phase of Kempegowda International Airport’s Terminal-2, scheduled for completion by 2029.
- the project aims to increase airport capacity by 20 million passengers annually, bringing its combined terminal capacity to approximately 80 million passengers per annum after completion.
- Scope of enabling works: site readiness, earthworks, removal of obstructing structures, road strengthening, setup of access points and barricades, tunnel management/maintenance, utility relocation, drainage setup.
- Phase one of Terminal-2 was inaugurated in 2022; domestic operations began January 2023 and international operations started September 2023.
- Fairfax India Holdings Corporation (74% equity owner in BIAL) also intends to develop a third terminal by fiscal year 2034. Combined future terminal capacities are projected beyond 90 million passengers annually.
Indian Opinion Analysis
The expansion at Kempegowda International Airport through terminal-2’s second phase reflects strategic efforts to address rising passenger traffic and enhance India’s aviation infrastructure. Completion by fiscal year 2029 aligns with long-term national priorities as air travel continues to grow steadily post-COVID recovery.
Moreover, the proposed third terminal (expected by FY2034) signals sustained confidence in Bengaluru as a business hub and tourist destination while reinforcing its position on India’s global connectivity map. These upgrades could bolster economic activity locally while reducing operational strain across other major airports nationwide.
Potential challenges may include managing construction timelines effectively without disrupting ongoing airport operations or causing passenger inconvenience during expansions. Though, rigorous planning coupled with advanced project management techniques might mitigate these risks effectively.