# Supreme Court restores contractor’s arbitral award against Kolkata Port Trust

2026-11-20T15:02:31+00:00 | Governance | Indian Opinion Desk

Corroboration: 2 independent outlets
Outlets counted: livelaw.in, verdictum.in

The Supreme Court has set aside a Calcutta High Court Division Bench order that reduced an arbitral award in favour of dredging contractor Marino Dredgeco by 50%, holding that a court exercising jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, cannot interfere with an award merely because the amount granted for additional work appears excessive. The Court said the High Court's conclusion that the claim for additional work shocked its conscience was not a legally sustainable ground for modifying the award. A bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran restored the award, noting that the additional work was essentially re-dredging of the same channel and basin to keep it operational, and that the High Court had mechanically exercised its jurisdiction without providing substantive reason. The Court reiterated that Section 37 does not permit a merits-based review, and that a government entity cannot receive special treatment merely because the amount awarded against it appears excessive. The dispute arose from a contract awarded by the Kolkata Port Trust for dredging at Sagar Island.

## Indian Opinion Analysis

Both livelaw.in and verdictum.in reported the judgment in neutral terms, focusing on the legal reasoning that a court under Section 37 cannot modify an award solely because the quantum shocks its conscience, and that government entities are not entitled to special treatment. Livelaw.in emphasised the Supreme Court's observation that the High Court had not looked at the nature of the additional work, while verdictum.in highlighted the Court's conclusion that the modification was not within the contours of Section 37 jurisdiction. Neither outlet added editorial gloss or critical framing. The uniform coverage reflects straight reporting of the ruling. The key takeaway is the reaffirmation of the limited grounds for interference under the Arbitration Act, with the award now fully restored.

## Coverage

Coverage: 2 sources, 2 neutral
- livelaw.in (neutral report) <https://www.livelaw.in/supreme-court/shocking-the-conscience-not-enough-to-modify-arbitral-award-supreme-court-restores-contractors-claim-against-kolkata-port-trust-559316>
  Reports Court's legal reasoning without editorial slant
- verdictum.in (neutral report) <https://www.verdictum.in/supreme-court/ms-marino-dredgeco-limited-v-the-board-of-trustees-of-the-port-of-kolkata-2026-insc-1238-1626124>
  Straight reporting focused on the legal principle

This brief was synthesised by AI from the 2 sources linked above, so one read covers every framing they carry.

Tags: Arbitration and Conciliation Act 1996, Justice J.B. Pardiwala, Kolkata Port Trust, Supreme Court of India
Canonical: https://indianopinion.org/supreme-court-restores-contractors-arbitral-award-against-kolkata-port-trust/
License: Summary and commentary (c) Indian Opinion, reusable with attribution. Facts belong to the linked sources.
Cite: https://indianopinion.org/supreme-court-restores-contractors-arbitral-award-against-kolkata-port-trust/#story-in-brief

Review state: not offered to search indexes, readable and citable here.

How this brief was made: an AI model read the reports linked above and wrote this summary and analysis, which were published automatically. Published briefs are sampled every hour by an automated quality check; the editor verifies its findings and approves corrections, and corrected briefs carry a dated correction line. Stance labels are editorial classifications of how each outlet framed this story, assigned by the same model, not ratings of the outlets. We do no original reporting. Methodology: https://indianopinion.org/ai-use-policy/