Bhiwandi will receive an additional 100 million litres per day (MLD) of water from Bhatsa dam, the Brihanmumbai Municipal Corporation (BMC) said. BMC on Wednesday (18 November 2026) approved leasing two plots of land, totalling about 12 acres, to Bhiwandi-Nizampur City Municipal Corporation (BNCMC) for 30 years to facilitate the project.

BNCMC will pay around Rs 40.56 crore for the lease. The land will host pumping stations, reservoirs, a water treatment plant and pipeline infrastructure under the Centre's AMRUT 2.0 programme.
The city's population has crossed 12 lakh, with daily demand at 162 MLD against a current supply of 115 MLD. Samajwadi Party MLA Rais Shaikh, who pursued the proposal for 18 months, said once completed, the project should meet demand until 2052.
Bhiwandi's 47 MLD deficit will be erased by the new 100 MLD allocation, but the project hinges on land acquisition, tendering and construction timelines the source does not give. The 30-year lease and Rs 40.56 crore payment are upfront costs, the overall scheme cost and completion date remain unstated. The source frames the announcement as a political win for MLA Rais Shaikh after an 18-month campaign, but leaves open when residents will actually see the first additional litre.
Source: timesofindia.indiatimes.com
This brief was synthesised by AI from the source linked above. Methodology and corrections.