The Airports Authority of India has informed the Meghalaya High Court that expansion work at Shillong Airport has commenced, with earth-moving machinery deployed for runway extension and demolition of staff quarters started for terminal expansion.

The court, perusing a status report, noted the contractor has deployed excavators and other equipment. The terminal expansion will extend into the AAI residential colony, and demolition of the existing residential building has begun.
The state government said against the required 16 acres for the runway end safety area, 17.68 acres have been acquired on the RWY 04 side. The PWD is preparing cost estimates for an access road to neighbouring villages. The next hearing is on 14 December.
Both outlets report the same facts in near-identical wire style, leading with the start of work and the court's observations. The Shillong Times adds more detail on the land acquisition and the PWD's road estimates, while Highland Post compresses the account. There is no divergent framing: both present the AAI and state government statements without scrutiny or challenge. A balanced reading is straightforward: the court has accepted the status report, work is physically underway, and the land shortfall on the isolation bay (6 acres required) is not addressed in the reports. The concrete point to watch is the 14 December hearing, when the court will assess further progress.
Coverage: 2 sources, 2 neutral
Sources (2): theshillongtimes.com (neutral report), highlandpost.com (neutral report)
This brief was synthesised by AI from the 2 sources linked above, so one read covers every framing they carry. Methodology and corrections.