Texas Governor Greg Abbott has temporarily halted approvals for new data centres seeking connections to the state’s electricity grid. He has ordered the Public Utility Commission and ERCOT to audit projects already…
Texas Governor Greg Abbott has temporarily halted approvals for new data centres seeking connections to the state’s electricity grid. He has ordered the Public Utility Commission and ERCOT to audit projects already in the interconnection queue before further approvals. Developers must disclose projected electricity demand, power generation, water use, cooling methods, tax incentives, ownership and plans to limit community impacts, The Times of India reports.
ERCOT says more than 1,800 projects are awaiting grid connections, representing over 474 gigawatts of demand, more than five times Texas’s record peak. About 90% of new power requests come from data centres. Only 28 of 377 companies responded to a recent state survey on energy and water needs. ERCOT has postponed a transmission planning study while it reviews the order.
The easy narrative is that Texas is turning against artificial intelligence, or that the pause is merely political theatre. Neither follows from the order. The state is confronting a basic planning problem: proposed demand far exceeds its peak use, while companies supplied limited information on water and electricity needs. Audits are sensible, but vague reviews can become arbitrary barriers. The useful test is whether regulators publish project-level findings and whether the 474-gigawatt queue shrinks after verification.
Source: timesofindia.indiatimes.com